Region: PJM (ComEd Zone)
Project Type: Utility-Scale Wind Generation
Capacity: ~100 MW Class
Issue Type: System Stability / Short Circuit Ratio (SCR) Constraint
Savings: ~$160M (≈90% reduction in network upgrade cost)
The Challenge
A utility-scale wind project sought to interconnect into a constrained 138 kV network with significant existin
Region: PJM (ComEd Zone)
Project Type: Utility-Scale Wind Generation
Capacity: ~100 MW Class
Issue Type: System Stability / Short Circuit Ratio (SCR) Constraint
Savings: ~$160M (≈90% reduction in network upgrade cost)
The Challenge
A utility-scale wind project sought to interconnect into a constrained 138 kV network with significant existing generation concentration and limited outlet capacity. Interconnection studies identified:
Very low Short Circuit Ratio (SCR ≈ 1.7) at a critical 138 kV substation
A weak system condition vulnerable to stability issues under N-1 contingencies
High sensitivity to a single 138 kV line outage
Total generation in the area approaching ~670 MW across only two grid outlets
Under traditional planning assumptions, the project triggered a major transmission expansion.
Traditional Utility Mitigation Outcome
The initial mitigation approach required:
Construction of a new 138 kV transmission line from a neighboring substation
Capital cost of approximately $180 million
Long permitting, siting, and construction timelines. High schedule and execution risk relative to project size. This solution rendered the project economically marginal to non-viable.
EDGE-Style Alternative Approach (GET-Enabled)
Instead of accepting the default transmission build, the interconnection strategy focused on: Root-cause analysis of the constraint (SCR-driven stability, not thermal overload)
Identifying whether the system weakness could be addressed locally and dynamically
Evaluating grid-enhancing technology (GET) solutions that could modify line impedance and power flow during contingency conditions. A GET-based mitigation strategy was proposed and validated through stability analysis, demonstrating that: The N-1 stability issue could be resolved without adding a new transmission line. System strength could be improved by reducing effective impedance on the critical path. Reliability criteria could be met without increasing transfer limits beyond safe bounds
Outcome
Network upgrade cost reduced from ~$180M to ~$20M
~$160M in avoided transmission capital
Order-of-magnitude improvement in project economics. Significantly reduced schedule, permitting, and execution risk. A viable interconnection pathway aligned with utility reliability requirements
Region: PJM
Project Type: Utility-Scale Renewable Portfolio (Solar + Storage) Scope: 20+ Active Queue Projects
Total Network Upgrade Exposure: ~$3.8B
Primary Risk Driver: System Reliability Upgrades
Client Type: Infrastructure Investor / Platform Developer
An infrastructure investor evaluating a large PJM development portfolio
Region: PJM
Project Type: Utility-Scale Renewable Portfolio (Solar + Storage) Scope: 20+ Active Queue Projects
Total Network Upgrade Exposure: ~$3.8B
Primary Risk Driver: System Reliability Upgrades
Client Type: Infrastructure Investor / Platform Developer
An infrastructure investor evaluating a large PJM development portfolio faced material uncertainty around interconnection cost exposure.
While individual projects appeared attractive on a standalone basis, the portfolio as a whole carried:
Traditional diligence approaches treated these upgrades as fixed outcomes, offering little insight into which risks were structural versus potentially mitigable.
EDGE conducted a scoped, fixed-fee portfolio interconnection risk assessment focused on PJM TC2 projects.
Rather than redesigning projects, the analysis was structured to inform capital allocation decisions, with emphasis on:
The output was IC-ready and designed to support investor-level decision-making—not engineering rework.
The portfolio review revealed that:
While no single project redesign was performed, the analysis materially improved investment confidence and portfolio strategy.
This case illustrates a second core EDGE principle:
Interconnection risk is increasingly a portfolio-level investment issue, not a late-stage engineering problem.
In congested regions like PJM, understanding which costs are binary, which are structural, and which may be mitigablecan materially influence valuation, sequencing, and go/no-go decisions.
Smarter Sites. Faster Power. Lower Risk.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.